Friday, September 23, 2011
Project Server 2010 Browser Support
I found this interesting post regarding Browser support for Project Server 2010. This is very useful during your planning phase:
http://technet.microsoft.com/en-us/library/cc263526.aspx
Configuring Exchange Server 2007 or 2010 with MPS 2010
There are a few important URL's to be aware of when synchronizing Exchange Server 2007/2010 with Project Server 2010;
1. http://technet.microsoft.com/en-us/library/ff793352.aspx (Exchange Server 2010 Impersonation)
2. http://technet.microsoft.com/en-us/library/ee782548.aspx (Exchange 2007)
3. http://technet.microsoft.com/en-us/library/ff468700.aspx (Project Server 2010 and Exchange Server 2010)
1. http://technet.microsoft.com/en-us/library/ff793352.aspx (Exchange Server 2010 Impersonation)
2. http://technet.microsoft.com/en-us/library/ee782548.aspx (Exchange 2007)
3. http://technet.microsoft.com/en-us/library/ff468700.aspx (Project Server 2010 and Exchange Server 2010)
Friday, January 21, 2011
Project Server 2007 64-bit on Windows 2008 Server
Couple issues you might run into:
Issue 1: When running the setup for Project Server 2007 with all necessary You get the message that you need MOSS installed.
Solution: You must slipstream Office Server and WSS SP2 or have the SP2 installation files during installation.
Issue 2: You get prompted that IIS is not running during the configuration wizard, but you know you have it installed and running.
Solution: You must have the "IIS 6 Management Compatibility" feature enabled.
Issue 1: When running the setup for Project Server 2007 with all necessary You get the message that you need MOSS installed.
Solution: You must slipstream Office Server and WSS SP2 or have the SP2 installation files during installation.
Issue 2: You get prompted that IIS is not running during the configuration wizard, but you know you have it installed and running.
Solution: You must have the "IIS 6 Management Compatibility" feature enabled.
Thursday, January 13, 2011
Configuring Project Server 2007 Data-Analysis for Windows 7
When configuring Windows 7 client(s) for Project Server 2007/PWA, you must have all of the required components installed as described in the following kb article:
http://technet.microsoft.com/en-us/library/cc197552(office.12).aspx
Also, you must configure the following areas:
Control Panel > Credential Manager > Add a Windows credential
Fill in the required information for your organization.
Click Ok.
http://technet.microsoft.com/en-us/library/cc197552(office.12).aspx
Also, you must configure the following areas:
Control Panel > Credential Manager > Add a Windows credential
Fill in the required information for your organization.
Click Ok.