There are a few important URL's to be aware of when synchronizing Exchange Server 2007/2010 with Project Server 2010;
1. http://technet.microsoft.com/en-us/library/ff793352.aspx (Exchange Server 2010 Impersonation)
2. http://technet.microsoft.com/en-us/library/ee782548.aspx (Exchange 2007)
3. http://technet.microsoft.com/en-us/library/ff468700.aspx (Project Server 2010 and Exchange Server 2010)
Friday, September 23, 2011
Friday, January 21, 2011
Project Server 2007 64-bit on Windows 2008 Server
Couple issues you might run into:
Issue 1: When running the setup for Project Server 2007 with all necessary You get the message that you need MOSS installed.
Solution: You must slipstream Office Server and WSS SP2 or have the SP2 installation files during installation.
Issue 2: You get prompted that IIS is not running during the configuration wizard, but you know you have it installed and running.
Solution: You must have the "IIS 6 Management Compatibility" feature enabled.
Issue 1: When running the setup for Project Server 2007 with all necessary You get the message that you need MOSS installed.
Solution: You must slipstream Office Server and WSS SP2 or have the SP2 installation files during installation.
Issue 2: You get prompted that IIS is not running during the configuration wizard, but you know you have it installed and running.
Solution: You must have the "IIS 6 Management Compatibility" feature enabled.
Thursday, January 13, 2011
Configuring Project Server 2007 Data-Analysis for Windows 7
When configuring Windows 7 client(s) for Project Server 2007/PWA, you must have all of the required components installed as described in the following kb article:
http://technet.microsoft.com/en-us/library/cc197552(office.12).aspx
Also, you must configure the following areas:
Control Panel > Credential Manager > Add a Windows credential
Fill in the required information for your organization.
Click Ok.
http://technet.microsoft.com/en-us/library/cc197552(office.12).aspx
Also, you must configure the following areas:
Control Panel > Credential Manager > Add a Windows credential
Fill in the required information for your organization.
Click Ok.
Saturday, March 27, 2010
Disabling Compression in IIS with Windows 2008 R2
If you are having issues with the Project and Resource Centers after installing Project Server on Windows 2008 R2, you need to disable compression in IIS.
Step by step to follow.
Step by step to follow.
Friday, December 11, 2009
Dont forget to "Remember Me"
Scenario: Project Managers working with Data-Analysis in Project Server 2007.
Issue: Two users with the identical user rights attempting to view and work with Data-Analysis views. One user is able to access views without issue while the other gets a message regard a "Transport Layer" issue. Micrsoft Knowledge Base points to similar issues arising when attempting to connect to Analysis Services when working in a Workgroup setting. The blogsphere and community see a similar issue when have the wrong or missing component like MSXML 6.0 or lack of SP1. None of these situations applied to this issue.
We concluded that the user had the proper rights and that Data-Analysis was properly configured based on our testing. The one caveat was that the users would log into their machines locally (due to a policy on their client site) when accessing the Project Server environment.
As we worked through the troublshooting, we focused on the fact that the users were being prompted to login into PWA, because they were logging into their machines locally. One of the users checked off the "Remember Me" option when logging on while the other user left it unchecked when coming into PWA and that was the solution to the issue. The credentials were not being passed to Analysis Services and therefore throwing an error, even though the client was able to see all other areas of PWA.
It was the perception of the client to realize this subtle difference and recognize the solution was just a check box away. "You rock Kathy!"
Issue: Two users with the identical user rights attempting to view and work with Data-Analysis views. One user is able to access views without issue while the other gets a message regard a "Transport Layer" issue. Micrsoft Knowledge Base points to similar issues arising when attempting to connect to Analysis Services when working in a Workgroup setting. The blogsphere and community see a similar issue when have the wrong or missing component like MSXML 6.0 or lack of SP1. None of these situations applied to this issue.
We concluded that the user had the proper rights and that Data-Analysis was properly configured based on our testing. The one caveat was that the users would log into their machines locally (due to a policy on their client site) when accessing the Project Server environment.
As we worked through the troublshooting, we focused on the fact that the users were being prompted to login into PWA, because they were logging into their machines locally. One of the users checked off the "Remember Me" option when logging on while the other user left it unchecked when coming into PWA and that was the solution to the issue. The credentials were not being passed to Analysis Services and therefore throwing an error, even though the client was able to see all other areas of PWA.
It was the perception of the client to realize this subtle difference and recognize the solution was just a check box away. "You rock Kathy!"
Tuesday, November 24, 2009
Installing EPM 2010
Couple items to be aware of as you look to install the Public Beta of Project Server 2010:
1. You will need SharePoint Server 2010
a. You will need to install the Standalone version if your not using AD. (It will not accept local accounts)
b. Be ready to install components outside of the prerequisites utility that comes with the setup.
-Powershell
-Geneva Framework
1. You will need SharePoint Server 2010
a. You will need to install the Standalone version if your not using AD. (It will not accept local accounts)
b. Be ready to install components outside of the prerequisites utility that comes with the setup.
-Powershell
-Geneva Framework
Sunday, October 18, 2009
Friday, October 16, 2009
Looks like the ribbon is here to stay-even for MS Project
This is a good link to get started learning about the new ribbon in Project 2010. We will be scheduling a webinar in November demonstrating and talking about the new functionality found in the ribbon with Project 2010:
http://blogs.msdn.com/project/archive/2009/09/24/project-2010-introducing-the-ribbon.aspx
Enjoy!
http://blogs.msdn.com/project/archive/2009/09/24/project-2010-introducing-the-ribbon.aspx
Enjoy!
Tuesday, October 13, 2009
Corrupt Cache is improperly displaying Custom Fields in Project Professional
The wrong custom field values are displaying in the Project Professional client. PWA is displaying the values correctly.
Verify:
1. You have the same SP applied to the client and the server(s)
2. Clear the cache on the client machine:
a. Run the command %appdata% in the Run dialog.
b. In the Application Data dialog, navigate to the folder Microsoft\MS Project\Cache.
c. Delete all of the files in this directory.
Verify:
1. You have the same SP applied to the client and the server(s)
2. Clear the cache on the client machine:
a. Run the command %appdata% in the Run dialog.
b. In the Application Data dialog, navigate to the folder Microsoft\MS Project\Cache.
c. Delete all of the files in this directory.
Upgrading to IE 8 and unable to display grid in Project and Resource Centers
After upgrading to IE 8, you are unable to download the Active X control to display grids in Project and Resource Centers:
Follow these steps:
1. Start Internet Explorer.
2. On the Tools menu, click Internet Options.
3. Click the General tab, and then click Settings in the Browsing history section.
4. Click View Objects.
5. Right-click Pj12enuC Class, and then click Remove.
6. Right-click PjAdoInfo4 Class, and then click Remove.
7. Close the View Objects window, and then click OK two times
Follow these steps:
1. Start Internet Explorer.
2. On the Tools menu, click Internet Options.
3. Click the General tab, and then click Settings in the Browsing history section.
4. Click View Objects.
5. Right-click Pj12enuC Class, and then click Remove.
6. Right-click PjAdoInfo4 Class, and then click Remove.
7. Close the View Objects window, and then click OK two times
Thursday, July 30, 2009
HotFix: KB 946517
If you recieve the following error:
Access to the path 'C:\WINDOWS\system32\drivers\etc\HOSTS' is denied.
or
Reason: "Attempted to read or write protected data"
Try installing the following HotFix:
http://support.microsoft.com/kb/946517
We recieved these errors after a new medium farm build and the hotfix solved the problem.
Access to the path 'C:\WINDOWS\system32\drivers\etc\HOSTS' is denied.
or
Reason: "Attempted to read or write protected data"
Try installing the following HotFix:
http://support.microsoft.com/kb/946517
We recieved these errors after a new medium farm build and the hotfix solved the problem.
Tuesday, June 09, 2009
Configurating Data-Analysis in Project Server 2007 with SQL Server 2008
Configurating Data-Analysis in Project Server 2007 with SQL Server 2008
It is important to understand that the following Microsoft KB Guidance for configuring Data-Analysis needs some important additions and considerations:
http://technet.microsoft.com/en-us/library/dd285466.aspx
First lets look at the following requirements:
"The way to install the DSO library is to get a set of redistributable packages included in the SQL Server 2005 Feature Pack. That set consists of:
Microsoft SQL Server Native Client
Microsoft SQL Server 2005 Management Objects Collection
Microsoft SQL Server 2005 Backward Compatibility Components"
It is important to install the Microsoft SQL Server Native Client for SQL Server 2008. This is due to the "Provider" that we use in the setup of Analysis Services.
The remaining components need to be from the 2005 Feature Pack.
Also, keep in mind that the OLAPUsers Group that we knew in 2005 is now called:
SQLServerMSASUser$
This is important when referencing the following step:
Add the SSP account to the OLAP users group
When you install SQL Server 2008 Analysis Services, a local group is created on the server that allows users to access it. This group is named SQLServerMSASUser$$MSSQLSERVER. You must add the SSP account to this group.
Everything else in the KB should be good to follow.
It is important to understand that the following Microsoft KB Guidance for configuring Data-Analysis needs some important additions and considerations:
http://technet.microsoft.com/en-us/library/dd285466.aspx
First lets look at the following requirements:
"The way to install the DSO library is to get a set of redistributable packages included in the SQL Server 2005 Feature Pack. That set consists of:
Microsoft SQL Server Native Client
Microsoft SQL Server 2005 Management Objects Collection
Microsoft SQL Server 2005 Backward Compatibility Components"
It is important to install the Microsoft SQL Server Native Client for SQL Server 2008. This is due to the "Provider" that we use in the setup of Analysis Services.
The remaining components need to be from the 2005 Feature Pack.
Also, keep in mind that the OLAPUsers Group that we knew in 2005 is now called:
SQLServerMSASUser$
This is important when referencing the following step:
Add the SSP account to the OLAP users group
When you install SQL Server 2008 Analysis Services, a local group is created on the server that allows users to access it. This group is named SQLServerMSASUser$
Everything else in the KB should be good to follow.
Tuesday, March 25, 2008
Ed Horn our Senior EPM Trainer beats my score with a 911
Ed Horn recently passed the MCTS 070-0632 exam with a 911. Although I feel happy for him and the good job he did with the exam, I am also concerned it will be brought up every time we co-teach a class...;)
Good job, Ed!
Good job, Ed!
Passed MCTS 070-0632 with a 900
The MCTS exam for Managing Projects with MS Project Professional is definately not a trivial exam. This is not a typical "office" exam. The questions in this exam require you to have a deep understanding of MS Project Professional 2007. If you are prepping with Transcendor or other Prep packages you might see some questions on earned value and the expected need to know alot about the formulas behind PV, EV, AC, etc. I personally only had one question on Earned Value formulas. You need to understand how task type settings work and what happens when resources are added and removed. You also need to understand dependency types and their influence when tasks get shifted around.
Overrall, it is a good exam and requires a breadth of knowledge to pass.
Overrall, it is a good exam and requires a breadth of knowledge to pass.
Sunday, March 09, 2008
Portfolio Server 2007 SP1 released!
Project Portfolio Server 2007 SP1 released.
I think there may have been some confusion about the release of PPS SP1. Some of you may have thought that it was part of the earlier Office Server SP1 release. The update was published on 3/6/2008 and there are quite a few fixes.
The update itself is relatively straight forward compared to Project Server. It can be found here:
http://www.microsoft.com/downloads/details.aspx?familyid=7cf44f2c-49d5-4431-bd3e-a10035ec1a39&displaylang=en
Its simply a matter of running the update and a Reboot is required.
I think there may have been some confusion about the release of PPS SP1. Some of you may have thought that it was part of the earlier Office Server SP1 release. The update was published on 3/6/2008 and there are quite a few fixes.
The update itself is relatively straight forward compared to Project Server. It can be found here:
http://www.microsoft.com/downloads/details.aspx?familyid=7cf44f2c-49d5-4431-bd3e-a10035ec1a39&displaylang=en
Its simply a matter of running the update and a Reboot is required.
Thursday, March 06, 2008
Clearing the Queue in Project Server
Sometimes the queue in Project Server 2007 appears to be getting hung up and you find that jobs are not completing successfully from Project Professional. The first steps to take are:
1. Click “Server Settings”
2. Click “Manage Queue”
3. Expand the “Advanced Options” section and ensure that the “Cancel jobs getting enqueued” option is checked.
4. Check the box next to the task you want to cancel and click the “Cancel Jobs” button.
If this still doesnt appear to help then you should:
1. Launch Services
2. Stop the Project Queue Service
3. Stop the SharePoint Timer Service
4. Start the SharePoint Timer Service
5. Start the Project Queue Service
1. Click “Server Settings”
2. Click “Manage Queue”
3. Expand the “Advanced Options” section and ensure that the “Cancel jobs getting enqueued” option is checked.
4. Check the box next to the task you want to cancel and click the “Cancel Jobs” button.
If this still doesnt appear to help then you should:
1. Launch Services
2. Stop the Project Queue Service
3. Stop the SharePoint Timer Service
4. Start the SharePoint Timer Service
5. Start the Project Queue Service
Wednesday, March 05, 2008
Online and Free Project Server Seminars
MS Project Pros has recently announced that it will offer ongoing free online seminars on various topics covering MS Project Server 2007 and the EPM offering. The topics will be 100-300 level depending on the topics. We will cover installation, configuration, troubleshooting and best practices among other things.
Thursday, February 28, 2008
Finding the document URL in MS Office
While working with SharePoint and Office 2007 you often want to locate the URL of the document you are working with. In Office 2003/WSS 2.0 that was much easier to find. If Office 2007 they tucked it away.
Here are the steps for adding it to your Quick Access Toolbar.
1. Locate the Quick Access Toolbar
2. Click the Customize Quick Access Toolbar
3. Click More Commands
4. On the Choose Commands from:
5. Choose All Commands
6. Scroll down to find Document Location
7. Click the Add button
8. Click Ok
Now you can copy and past the document URL Location.
Here are the steps for adding it to your Quick Access Toolbar.
1. Locate the Quick Access Toolbar
2. Click the Customize Quick Access Toolbar
3. Click More Commands
4. On the Choose Commands from:
5. Choose All Commands
6. Scroll down to find Document Location
7. Click the Add button
8. Click Ok
Now you can copy and past the document URL Location.
Managing Change Requests with Content types
Your team can manage change requests with SharePoint by Using Office templates and Content Types. First learn how to enable and use content types with SharePoint:
Here is a good article on how to do that:
http://www.bobmixon.com/blog/Lists/Posts/Post.aspx?ID=44
You can then add custom workflow to the document library so that every request that get made gets routed to the PMO and Project Server administrator.
Here is a good article on how to do that:
http://www.bobmixon.com/blog/Lists/Posts/Post.aspx?ID=44
You can then add custom workflow to the document library so that every request that get made gets routed to the PMO and Project Server administrator.
Monday, February 25, 2008
Upgrading to SP1 in a medium farm and having a snapshot restored to an earlier instance
We recently had a situation where an environment we support was upgraded to SP1. Everything went as planned. The MOSS admin VM instance then became corrupted. After investigating the log files we got a message related to the Schema being "inconsistent". This told us that the snapshot that was restored was earlier then the one that had the SP applied to it.
The simple solution was to apply the Service pack to the MOSS instance and it worked perfectly. Just apply the SP the same way you applied it the first time.
The simple solution was to apply the Service pack to the MOSS instance and it worked perfectly. Just apply the SP the same way you applied it the first time.
Subscribe to:
Posts (Atom)